Replacement of switching equipment at transformer substation TP-2905
- Bringing project documentation (2013) into line with current standards and requirements.
- Palace employees replaced the automatic reserve input on the main distribution board, and the system is now operating reliably.
- Repair work on the main distribution board to replace the 1959 motor-driven automatic circuit breakers with new ones.
- Laying of control and alarm circuit cables.
- Installation of a new AVR (automatic reserve input) panel.
- Debugging and commissioning of new equipment. Manufacture and installation of new panel equipment in RU 0.4kV TP-2905.
- All equipment is designed with the possibility of subsequent installation of dispatching systems.